2014 Capital Needs Projects Almost Done

Winston-Salem bonds logoIn November 2014 city voters approved $139.2 million in general obligation bonds to finance unmet capital needs in the areas of public safety, recreation and parks, streets and sidewalks, economic development, and housing.

Of the 42 projects approved in the bond referendum, 40 are completed, under construction or out for bid as of October 2018. This includes all 19 recreation projects, all eight public safety projects, and all but two of the 10 street and sidewalk projects on the ballot. Not yet underway: the Business 40 Corridor Improvements, which will be part of the rebuild of Business 40 about to get underway; and the Meadowlark Drive widening, which will be rebid after the first of the year.

In addition, renovations and expansion of the Benton Convention Center have been completed, and restoration of the historic Union Station is scheduled for completion by the end of the year. These projects were financed with $35.8 million in limited obligation bonds.

2014 bond project map40 of the 42 bond projects voters approved in 2014 are completed, under construction or under contract. Map does not show locations of street repaving and sidewalk projects. Numbers correspond with projects listed below. See a larger view of the map.


Project / Status

Recreation (on the Bond Tracker site, find Categories under the large map and choose "Recreation")

1. Jamison Park / Completed Groundbreaking photos | Groundbreaking video
2. Sedge Garden Community Center gym / Completed Groundbreaking photos | Groundbreaking video
3. Piney Grove / Completed
4. Bowen Park/ Completed Groundbreaking photos | Groundbreaking video
5. Quarry Park/Waughtown Greenway Connector / Completed Groundbreaking video | Groundbreaking photos
6. Winston Lake Aquatic Facility / Completed Groundbreaking video | Groundbreaking photos
7. The Gathering Place at Fairview Park / Completed
8. Salem Lake Marina / Completed Groundbreaking photos | Groundbreaking video
9. Water Spraygrounds / Sedge Garden, Rupert Bell, Little Creek Park, Hathaway Park, Reynolds Park, Polo & Mineral Springs completed; Parkland under construction.
10. Winston Lake Golf Course / Projected completion March 2019
11. Kimberley Park / Completed
12. Miller Park / Under construction Miller Park stream restoration video | Miller Park stream restoration photos.
13. Blum Park / Completed
14. Hobby Park / Completed
15. Carver tennis courts / Completed
16. Happy Hill Park / Contract awarded
17. Parkland Pool & Tennis Courts / Under construction
18. Hanes Park / Under construction
19. Parkland Acquisition (Second Street Park, Malloy Park, West Ward Pocket Park) / Acquisition completed; Second Street Park & Malloy Park now under construction with other funds

Public Safety (on the Bond Tracker site, find Categories under the large map and choose "Public Safety")

20. District 3 Police Station / Completed
21. Fire Station No. 7 / Completed Groundbreaking video | Groundbreaking photos
22. Fire Station No. 9 / Completed Groundbreaking video | Groundbreaking photos
23. District 2 Police Station / Completed Groundbreaking photos | Groundbreaking video
24. Fire Station No. 8 / Completed Groundbreaking photos | Groundbreaking video
25. Beaty Public Safety Training and Support Center / Completed
26. District 1 Police Station / Completed Groundbreaking video | Groundbreaking photos
27. Public Safety Center Renovations / Under contract

Streets and Sidewalks

Street Resurfacing / Completed. Voters approved $15.25 million in bonds, which is being spread over the four contracts listed below:
Contract 1, completed. List of streets
Contract 2, completed. List of streets
Contract 3A, projected contract award March 2016. List of streets
Contract 3B, projected contract award March 2016. List of streets

Sidewalks / Voters approved $10 million in bonds. As of October, 2018, 31 of the 57 sidewalk projects are completed; 14 are in progress. Additional sidewalk projects are in the planning stages.

28. Polo Road Corridor Improvements / Completed Groundbreaking photos | Groundbreaking video
29. Concrete Base Street Rehabilitation / Completed
30. Meadowlark Drive Widening / Awaiting rebid
31. Old Salem Infrastructure Project / Under construction
32. Business 40 Corridor Improvements / Under construction

Bike, Pedestrian and Child Pedestrian Safety Projects / Voters approved $1.8 million in bonds for bicycle & pedestrian project matching funds and $2 million in bonds for child pedestrian safety projects. The projects listed below account for $282,000 of this. Five of eight projects initiated with this money are completed; the other three are projected for completion in June 2019. Details of Bike and Pedestrian Projects.

Economic Development

33. Economic Development Sites & Infrastructure / Thus far $10.37 million has been committed to the following projects: Union Cross Business Park spec building & road extension (completed), Hydroponics facility (under construction), Brookwood Business Park infrastructure (on-going), Whitaker Park infrastructure (in the planning stage), Lucia library/commercial site feasibility study (completed).
34. Merschel Plaza / Under construction
35. RUCA Phase III (Revitalizing Urban Commercial Areas) / Voters approved $2 million in bonds. To date projects totaling $1,487,725 have been approved at Patterson/Glenn, 14th St./New Walkertown Road and Old Greensboro Rd./Barbara Jane Ave.

Housing

36. Housing & Neighborhood Development / Voters approved $6 million in bonds. This money was allocated to four projects: 757 North Apartments is completed; Emmanual Retirement Village is under construction; New Hope Manor, Ridgewood Place are on-going.
37. Transforming Urban Residential Neighborhoods / Voters approved $4 million in bonds. To date $1.54 million has been approved for neighborhoods in the North, Northeast, East, Southeast and South wards.

Limited Obligation Bond Projects

38. Benton Convention Center / Completed Groundbreaking [video] | Groundbreaking photos
39. Union Station / Completion projected in December 2018 Groundbreaking photos | Groundbreaking video

inside convention centerinside the convention center