Sidewalk Projects

Voters approved $10 million in bonds to build sidewalks. The projects listed below account for $1.82 million of this. These projects are expected to be completed or under construction by the end of June 2016. Additional sidewalk projects are in the planning stages.

  1. Cole Road sidewalk from Cragmore to existing just south of Eastwood. Bond funding $300,000; total project $422,714. Under construction.
  2. Reynolds Park Road sidewalk and road widening, from Salem Lake Road to Kings Plaza. Bond funding $792,000; total project $1.09 million. Under construction.
  3. 25th Street sidewalk from Kirkwood to Thurmond Street, contract awarded with estimated completion by April 2016. $29,850.
  4. Chandler Street sidewalk from Apollo Drive to Old Greensboro Road. Estimate: $70,000 Projected to be started by March 2016.
  5. Gerald Street sidewalk from Addison Avenue to New Walkertown Road. Estimate: $75,000. Projected to be started by April 2016.
  6. Old Town Drive sidewalk to connect the two greenway sections. Estimate: $70,000. Projected to be started by June 2016.
  7. Robinhood Road sidewalk from Peace Haven Road to 3333 Robinhood Road. Estimate: $18,500. Projected to be completed by June 2016.
  8. Cherokee Lane sidewalk from Ebert Street to Magnolia Street. Estimate: $102,000. Projected to be completed by February 2016
  9. Old Vineyard Road sidewalk, from existing sidewalk at Johnsborough Court to Maureen Road. Estimate: $60,000. Projected to be started in March 2016.
  10. Yorkshire Road sidewalk, from Silas Creek Parkway to Wellington Road. Estimate: $139,500. Projected to be started by February 2016.
  11. Bryansplace Drive sidewalk from Allistair Road to Cedar Trail. Estimate: $165,000. Projected to be started by February 2016.