Maplewood Avenue Emergency Culvert Replacement

Project Update

Construction was complete on this project in October of 2022

 

About the Project

The city replaced two (2) fifty-four (54) inch drainage pipes between Knollwood and Bolton Streets. The pipes were failing and collapsing in the public right of way undermining the road and causing the road to be closed indefinitely. The failure resulted in a sinkhole being exposed in the street and other utilities being exposed because of the damages. 

This project improved the city’s stormwater system which makes it easier for water to flow when it rains.


Project Details

 

Project Type:              Drainage Improvement

Project Budget:           $500,000

Design Engineer:        City 

Contractor:                  Charles D. Lowder, Inc.

 

Schedule

 

Date 

Activity

Winter 2021

Project Design started

Spring 2022

Project Design Complete

Summer 2022

Construction Begins

Fall 2022

Construction Completed

 

Contact Us

For more information on this project, email Mr. Todd M. Love, City of Winston-Salem Stormwater Division, or call 336-734-1318.