May 12, 2022 10:04 AM

Systemwide sewer rehab closures: May 16

Work continues on the System-Wide Sewer Rehabilitation project in Winston-Salem. The following streets in Phase 4 will be closed to through traffic weekdays starting Monday, May 16, from 9 a.m. to 4 p.m.

• Main Street between Liberty and Sixth streets
• Buena Vista Road between Virginia and Hawthorne roads
• Virginia Road between Carolina Circle and Buena Vista Road

Only portions will be closed at any given time and lane closures will be used in lieu of road closures when possible. Work is expected to be completed by Friday, May 27. The contractor will post detours and motorists are encouraged to plan for alternate routes.

Details on capital improvement projects are posted at cityofws.org/cip. For more information, contact City Link at citylink@cityofws.org, call 336-727-8000 or use any of the methods on cityofws.org/citylink.

SW4 Rehab closures-May 16